Planned work of the cloud platform ru-8, 09/11/2023 from 06-09-23 16:58 MSK to 19-09-23 11:53 MSK
Scheduled maintenance
Cloud Platform
Services
Cloud servers
Data centers
Novosibirsk
Svetlyi
06-09-23 16:58 MSK
·
1 week, 5 days, 18 hours, 55 minutes
Updates
Resolved
September 19, 2023 · 11:51 MSK
The planned work was completed on September 12 at 01:30 Moscow time.
Scheduled
September 6, 2023 · 16:58 MSK
In connection with the planned update of the software components of the network equipment of the ru-8 pool, it is planned to work with the downtime of cloud routers up to 15 seconds.
Traffic passing through the cloud router will be affected, including incoming traffic to public IP addresses. Traffic entering IP addresses on public subnets will not be affected.
Work will be carried out from 11.09 22:00 to 12.09 03:00 local time (11.09 18:00 to 11.09 23:00 Moscow time).
Software updates are important for the security, performance, and functionality of your hardware.
We apologize for the inconvenience that may occur.